State Street Infrastructure Project Resumes Construction Next Week

Share

The State Street Infrastructure Project will be resuming construction work during the week of April 2, 2018.  Sargent Corp. finished installing all of the projects underground utilities before leaving the site in January.  It will return next week to complete curbing, sidewalk ramp installations, signal improvements and final paving.

Drivers and residents should expect lane closures for traffic delays on all project streets during construction hours of 7:00 am – 7:00 pm.

The contractor is required to complete these activities by June 30, 2018 based on the contract with the city.  The current schedule provided by the contractor shows the project being completed by the end of May 2018.

Please contact Justin Pellerin at jrp@portlandmaine.gov or at 207 – 874-8828.